9.10.2 Enhancements and Fixes
Enhancements
- Added aging to Unsolicited Change Requests in the Project Summary
Fixes
Project Summary
- Unsolicited Change Requests in the status of “Reviewed” did not display in the Project Summary
Progress Claim
- Included “Reviewed” status in the logic used to determine if a Progress Claim is newer (subsequent) or older (previous)
- When the Amount Claimed is equal to the Total Contract, rounding from previously issued Progress Claims causes the error “The amount claimed is more than the Total Contract”